SOCIAL

Kumbungu Assembly block to be completed next month - Alima
Minister for Local Government and Rural Development, Alima Mahama has indicated on the floor of Parliament that ending of December this year the Kumbungu Assembly block will be completed.

Date Created : 12/4/2017 5:58:51 AM : Story Author : Kwaku Sakyi-Danso/ghanamps.com

She further revealed that, the contractor has made known that 80 percent of work has been completed.

According to the sector Minister, so far GHc1, 274, 439.86 has been paid with GHc 658,963.44 outstanding as GHc 1,531,746.26 being the contract sum.

“Mr. Speaker the project was awarded in 22nd January, 2015 funded by the District Assembly Common Fund and was expected to be completed by April 2016”, she stated.